26.11.2024
Council Inspection
We’re pleased to advise that Council completed their inspection of Oceanic Tower as part of the Plan Sealing process on Tuesday, 26th November 2024. Council will now assess their observations against the relevant conditions of the development approval.
We look forward to advising you once the Plan is sealed which in turn will enable lodgement of titles to occur. In the meantime, we are pleased to share some photos of the pool which was recently filled.
6.11.2024
Plan Sealing lodgement!
We’re pleased to advise the Project Surveyor successfully lodged for Plan Sealing on Wednesday, 6 November 2024. Council will now assess the relevant documentation and carry out their necessary inspections of Oceanic Tower to ensure compliance with the development approval.
We look forward to advising you once the Plan is sealed which in turn will enable lodgement of titles to occur.
29.10.2024
Landscape Works
As per the attached photos. We’re pleased to inform you that all landscape works are now complete and underwent a council inspection on 25 October 2024. We are confident the lush greenery and thoughtfully designed outdoor spaces will provide you with a beautiful environment to enjoy for many years to come.
Tower Crane Removal
We have begun the process of removing the tower crane from the site. This significant milestone not only enhances the skyline but also signifies the building is at the final phase of construction.
Scaffold removal
All scaffold has now been removed from the lower levels of Oceanic Tower enabling the remaining lower sections of the façade to now have their final coats of paint applied.
Final Cleans of Apartments